Difference between revisions of "Project com/en/"

From Help.4pm
Jump to navigationJump to search
Line 10: Line 10:
 
*''description ''- main project goals, text field
 
*''description ''- main project goals, text field
  
<span id="1371651775752S" style="display: none;">&nbsp;</span>obligatory fields (*)  
+
obligatory fields (*)  
 
 
Additional fields are available upon clicing '''show details''':
 
  
 +
click '''show details''' to show additional fields:
 
*''PROJECT ID ''- unique identifier, automatically created by 4PM  
 
*''PROJECT ID ''- unique identifier, automatically created by 4PM  
 
*''MAIN PROJECT FOR PROJECT GROUP ''- for management of ''activities ''or ''costs ''on the level of project group (programme)  
 
*''MAIN PROJECT FOR PROJECT GROUP ''- for management of ''activities ''or ''costs ''on the level of project group (programme)  

Revision as of 09:34, 27 June 2013

SOCRECARD

Main projec data to put project into organizational structure

  • project name* - descriptive name of the project.
  • project group* also used to put projects to programme, department, division.... Important for eventual integration 4PM-ERP system.
  • priority - drop-down list: 4 levels. Recommended internal rules.
  • project size - drop-down list: 4 levels. Recommended internal rules.
  • project status - drop-down list to label and group project through life cycle.
  • description - main project goals, text field

obligatory fields (*)

click show details to show additional fields:

  • PROJECT ID - unique identifier, automatically created by 4PM
  • MAIN PROJECT FOR PROJECT GROUP - for management of activities or costs on the level of project group (programme)
  • ANALYTICS
  • DEFAULT VAT
  • DEFAULT PAYMENT DUE

history of chaneges is hidden in detailed overiview, under the icon "hour". PROJECT OPENED BY

Main project participants

Overview of main project participants from project team.

4.1.2.IzkaznicaGlavniUdeleženci.jpg

Settings of project roles in the project scorecard are set in GENERAL / PARTICIPANTS / PERSONS' ROLE by selecting SHOW ON SCORECARD

4.1.2.IzkaznicadodajanjeVlogeOseb.jpg

Quick links to main parts of the project: participants, gantchart, finance scorecard, documents.

4.1.2.IzkaznicaPovezave.jpg

 Project plan & scoreboards

Display of additional fields in the scorecard should be activated in the general application settings. 4.1.2.IzkaznicaSemaforji.jpg

  • Planned hours: manually enter the card (do not take into account the number of hours allocated to individual tasks).
  • Planned start and end dates: manual entry.
  • Duration: automatic calculation of the number of quarters of the project: ((date-end date) / 91.25).

 

Temporal completion

  • COMPLETION PLAN BY TIMESHEET: the current date-start date / project duration - automatic calculation.

Past projects have a plan of realization of 100%.

  • Subjective assessment of project leader: manual entry by project manager and record of changes.

% COMPLETION OF PLANNED HOURS SUBJECTIVE ASSESSMENT - SCHEDULED REALIZATION PROJECT PROGRESS DELAY IN DAYS


4.1.2.IzkaznicaEvidencaSprememb.jpg

4.1.2.IzkaznicaPrikaziPodrobnost.jpg