Project work can be analysed by activities and by persons in tab PROJECT / RESOURCES / WORK BY ACTIVITIY.

4.1.3.realizacijaPoaktivnostih.jpg

  1. set period
  2. select persons. Add one or more persons from a list.
  • if no person is added, than all activities will be analysed.
  • label "activate filter by persons" enables separate display of persons (by columns)
  • label "Activate filter by time unit" enables separate display of selected time units (by columns)
  1. click SHOW to generate analytical overview.

The display can be modified by changing various filters and settings of this overiview. Table can be Exported to Excel.