=Project plan=
+
= Project plan =
* Project team members must perform certain activities to achieve project goals in set time frames. Project activities can be '''phases, work packages, tasks, milestones...'''
 
* Preparing '''project schedule''' and Gantt-chart is simultaneous with '''task and activity allocation''' to team members. All corrections (dates, content) are available to team members in real time, with no delays.
 
* Project team members use tasks for every-day '''collaboration and communication''' (entering comments, uploading and sharing project documents) and '''reporting''' (task progress reporting, hours done)
 
* All information is archived, organized and available to use. All communication can be also sent by e-mails.
 
  
Project course is scheduled in 4PM and at the same time tasks and assignments are allocated to 4PM users in a transparent manner (in 4PM and by e-mail).
+
*Project team members must perform certain activities to achieve project goals in set time frames. Project activities can be '''phases, work packages, tasks, milestones...'''
 +
*Preparing '''project schedule''' and Gantt-chart is simultaneous with '''task and activity allocation''' to team members. All corrections (dates, content) are available to team members in real time, with no delays.
 +
*Project team members use tasks for every-day '''collaboration and communication''' (entering comments, uploading and sharing project documents) and '''reporting''' (task progress reporting, hours done)
 +
*All information is archived, organized and available to use. All communication can be also sent by '''e-mails'''.
  
==How to plan project schedule==
+
Project course is scheduled in 4PM and at the same time tasks and assignments are allocated to 4PM users in a transparent manner (in 4PM and by e-mail).  
Project schedule (Gantt-chart) is made by the use of phases, tasks and milestones:
 
* '''phase''' is created by clicking the icon [[file:4.3.ikonaDodajFazo.jpg]],
 
* '''task''' click [[file:4.3.ikonaDodajNalogo.jpg]]; to delegate task to one or more team members it should be assigned to project participants (add).
 
* '''milestone''' click [[file:4.3.ikonaUstvariMejnik.jpg ]],
 
* '''meeting''' click [[file:4.3.ikonaSkliciSestanek.jpg]]
 
* Import and Export to Excel [[file:4.3.ikonaIzvozInUvoz.jpg]]
 
* click [[file:4.3.ikonaDodaj(zelenKrogPlus).jpg]] to add child activity to phase.
 
[[file:4.3.PotekProjekta.jpg|600px|]]
 
  
==Management of project phases ==
+
== How to plan project schedule ==
Phase can be:
+
[[File:Project_task_milestone_tree.JPG|600px|thumb]]
* a group of similar project activities (work package, WP)
+
Project schedule (Gantt-chart) is made by the use of phases, tasks and milestones:
* group of activities in narrower time limit
 
* smaller project (sub project)...
 
  
===New phase===
+
*'''phase''' is created by clicking the icon [[Image:4.3.ikonaDodajFazo.jpg]],
 +
*'''task''' click [[Image:4.3.ikonaDodajNalogo.jpg]]; to delegate task to one or more team members it should be assigned to project participants (add).
 +
*'''milestone''' click [[Image:4.3.ikonaUstvariMejnik.jpg]],
 +
*'''meeting''' click [[Image:4.3.ikonaSkliciSestanek.jpg]]
 +
*Import and Export to Excel [[Image:4.3.ikonaIzvozInUvoz.jpg]]
 +
*click [[Image:4.3.ikonaDodaj(zelenKrogPlus).jpg]] to add child activity to phase.
  
# click icon [[file:4.3.ikonaDodajFazo.jpg]] to open form.
+
== Management of project phases  ==
# enter '''phase name''' and '''abbreviation'''
 
# select head of phase (from the list of participants),
 
# planned hours of work (optional)
 
# planned start and end date
 
and short description
 
  
[[file:4.3.1.DodajFazo.jpg|400px|]]
+
Phase can be:  
  
* Each phase can have any number of '''sub-phases'''.[[file:4.3.ikonaDodajFazo.jpg]]
+
*a group of similar project activities (work package, WP)
* Head of the phase receives milestone for the phase end date.
+
*group of activities in narrower time limit
 +
*smaller project (sub project)...
  
===Phase and cost planning and cost monitoring===
+
=== New phase ===
# financial plan and cost can be monitored at the level of individual phases.
 
#*If financial plan is inserted first, later added phases inherit planned costs types in the value of 0. In this case, you can monitor the level of implementation of each phase, a comparison of the plan and implementation is at the level of the project.
 
# Financial plan and implementation can be monitored on the level of individual phase (work package).
 
## enter project activity plan by phases and activities (Gantt chart, project schedule)
 
## connect project activities with financial plan.
 
This is important for project management and reporting for co-financed projects.
 
  
==Task management==
+
[[File:Phase_edit_new.JPG|400px|thumb]]
Task is basic unit of the project with allocated resources. It represents an activity that is necessary to achieve project goal(s).
+
#click icon [[Image:4.3.ikonaDodajFazo.jpg]] to open form.
 +
#enter '''phase name''' and '''abbreviation'''
 +
#select head of phase (from the list of participants),
 +
#planned hours of work (optional)  
 +
#planned start and end date
 +
# and short description.
  
4PM uses task to:
+
[[File:Phase_view.JPG|thumb]]
#''' schedule project activities'''. Each task has set duration (start and end date), it has content (what to do) and one or more assigned participants. Task progress and status can be monitored
 
#'''collaboration and communication''' - by exchanging task comments and task documents. Integrated e-mailing systems enables effective communication in the group.
 
#''' daily reporting on work progress''' - each team member can access all relevant task information: task due date, allocated time and time spent, task progress of co-workers. Simple reporting forms enable time effective daily reporting and communication tool. Once a task is completed, a status is changed and notification sent to project manager.
 
  
===New task===
+
*Each phase can have any number of '''sub-phases'''.[[Image:4.3.ikonaDodajFazo.jpg]]  
Click icon [[file:4.3.ikonaDodajNalogo.jpg]] to open form.
+
*Head of the phase receives milestone for the phase end date.
''New tasks can be added in My 4PM/Insert/new task.''
 
# select '''activity''' for task performance. Use list of project activities.
 
# enter task name (short description).
 
# set start and end date for the task.
 
#* if activity has set general duration (please check General/classification/list of activities) then application suggests end date (it can be changed)
 
#* if '''warning display for dates''' is on, then all dates must be within parent activity (phase, project)
 
#* if task does not have planned end date and allocated hours, it cannot used for resource load planning.
 
# optionally enter '''task description''' and
 
# attach '''links to documents'''
 
# select organization
 
# add assignees:
 
#* project participants (one or more) or
 
#* working groups (must be added to project).
 
# add number of available hours for a task for each individual
 
# optionally enter individual's task description (double click + confirm)
 
# confirm by '''ADD''
 
# save and send e-mail notification to all task members.
 
  
===Edit task===
+
=== Phase and cost planning and cost monitoring ===
To change dates, add new task members, change description, add a comment, click task name to open task form in: any list of tasks, Gantt-chart, project course...
 
Click [[image: 2.2.2.ikonaSvincnik.jpg‎]] to open task for editing.
 
  
Task details are accessible by clicking [[image: 2.2.2.ikonaLupa.jpg‎]]:
+
#financial plan and cost can be monitored at the level of individual phases.  
* parent phase of the task
+
#*If financial plan is inserted first, later added phases inherit planned costs types in the value of 0. In this case, you can monitor the level of implementation of each phase, a comparison of the plan and implementation is at the level of the project.
* task reporter,
+
#Financial plan and implementation can be monitored on the level of individual phase (work package).
* task duration,
+
##enter project activity plan by phases and activities (Gantt chart, project schedule)  
* list of task participants (assigned to) and state of task (task progress estimation)
+
##connect project activities with financial plan.
  
===Task and documents===
+
This is important for project management and reporting for co-financed projects.  
Task can have links to documents:
 
* that are up-loaded to 4PM (folder ''Tasks'' or any other project sub-folder that user can access
 
* direct up-load to task in the field ''description'' or ''comments''.
 
  
===Task and comments - collaboration===
+
== Task management ==
  
Team communication and collaboration is by '''task comments''':
+
Task is basic unit of the project with allocated resources. It represents an activity that is necessary to achieve project goal(s).
* comments entered on a task (edit)
 
* comments at project work reporting (daily description of work on task)
 
* comments at task actions (accept, reject, done, finished, cancelled)
 
* automatic comments on task actions
 
  
Comments can have links to '''documents'''[[file: IkonaPriponka.JPG]]. Comments can be
+
4PM uses task to:  
# only saved to task or
 
# saved and sent by e-mail notification [[file:IkonaPismo.JPG]] to:
 
#* all team members
 
#* all task members
 
#* project manager.
 
  
[[file:4.3.1.DodajKomentarNaNalogo.jpg|400px|]]
+
#'''schedule project activities'''. Each task has set duration (start and end date), it has content (what to do) and one or more assigned participants. Task progress and status can be monitored
 +
#'''collaboration and communication''' - by exchanging task comments and task documents. Integrated e-mailing systems enables effective communication in the group.
 +
#'''daily reporting on work progress''' - each team member can access all relevant task information: task due date, allocated time and time spent, task progress of co-workers. Simple reporting forms enable time effective daily reporting and communication tool. Once a task is completed, a status is changed and notification sent to project manager.
  
===Tasks and EU Projects===
+
=== New task ===
Tasks on EU projects need to have set cost field. To plan project activities you need to put '''financial plan''' to 4PM first with '''planned personnel costs''' and cost fiels.
+
 
 +
Click icon [[Image:4.3.ikonaDodajNalogo.jpg]] to open form. ''New tasks can be added in My 4PM/Insert/new task.''
 +
 
 +
#select '''activity''' for task performance. Use list of project activities.
 +
#enter task name (short description).
 +
#set start and end date for the task.
 +
#*if activity has set general duration (please check General/classification/list of activities) then application suggests end date (it can be changed)
 +
#*if '''warning display for dates''' is on, then all dates must be within parent activity (phase, project)
 +
#*if task does not have planned end date and allocated hours, it cannot used for resource load planning.
 +
#optionally enter '''task description''' and
 +
#attach '''links to documents'''
 +
#select organization
 +
#add assignees:
 +
#*project participants (one or more) or
 +
#*working groups (must be added to project).
 +
#add number of available hours for a task for each individual
 +
#optionally enter individual's task description (double click + confirm)
 +
#confirm by '''ADD''
 +
#save and send e-mail notification to all task members.
 +
 
 +
=== Edit task ===
 +
 
 +
To change dates, add new task members, change description, add a comment, click task name to open task form in: any list of tasks, Gantt-chart, project course... Click [[Image:2.2.2.ikonaSvincnik.jpg]] to open task for editing.
 +
 
 +
Task details are accessible by clicking [[Image:2.2.2.ikonaLupa.jpg]]:
 +
 
 +
*parent phase of the task
 +
*task reporter,
 +
*task duration,
 +
*list of task participants (assigned to) and state of task (task progress estimation)
 +
 
 +
=== Task and documents ===
 +
 
 +
Task can have links to documents:
 +
 
 +
*that are up-loaded to 4PM (folder ''Tasks'' or any other project sub-folder that user can access
 +
*direct up-load to task in the field ''description'' or ''comments''.
 +
 
 +
=== Comments - collaboration ===
 +
 
 +
[[File:Task_comments.JPG|400px|thumb]]
 +
Team communication and collaboration is by '''task comments''':
 +
 
 +
*comments entered on a task (edit)
 +
*comments at project work reporting (daily description of work on task)
 +
*comments at task actions (accept, reject, done, finished, cancelled)
 +
*automatic comments on task actions
 +
 
 +
Comments can have links to '''documents'''[[Image:IkonaPriponka.JPG]]. Comments can be
 +
 
 +
#only saved to task or
 +
#saved and sent by e-mail notification [[Image:IkonaPismo.JPG]] to:
 +
#*all team members
 +
#*all task members
 +
#*project manager.
 +
 
 +
=== Tasks and EU Projects ===
 +
Tasks on EU projects need to have set cost field. To plan project activities you need to put '''financial plan''' to 4PM first with '''planned personnel costs''' and cost fiels.  
  
 
Same task can have various cost fields set (each assignment needs to have set cost field).  
 
Same task can have various cost fields set (each assignment needs to have set cost field).  
* '''double-click''' on the field '''cost field''' at assignment
 
* select planned cost field
 
* confirm [[File:4.2.9.ikonaKljukcaZelena.jpg]]
 
  
[[file:4.3.1.DodajNalogoKompleksniProjekti.jpg|500px]]
+
*'''double-click''' on the field '''cost field''' at assignment
 +
*select planned cost field
 +
*confirm [[Image:4.2.9.ikonaKljukcaZelena.jpg]]
  
===Task progress===
+
=== Task progress ===
4PM supports two possibilities to monitor task progress and execution:
 
*'''Automatic''' - assignment needs to have allocated (planned) hours (>0): task progress is automatically calculated at each '''work entry''' by formula: (hours done/allocated hours)*100.
 
*'''Manual''' - each task participant enters '''personal estimation''', which can be different from automatic.
 
  
====Colours of task progress====
+
4PM supports two possibilities to monitor task progress and execution:  
'''blue:'''
 
* Manual <= Automatic (Task progress is faster or the same as planned)
 
* closed assignments: 100 % progress
 
  
'''orange:'''
+
*'''Automatic''' - assignment needs to have allocated (planned) hours (&gt;0): task progress is automatically calculated at each '''work entry''' by formula: (hours done/allocated hours)*100.
* Automatic >= Manual (Task progress is slower)
+
*'''Manual''' - each task participant enters '''personal estimation''', which can be different from automatic.
* reported hours <= allocated hours
 
  
'''red:'''
+
==== Colours of task progress ====
* Automatic > Manual (Task progress is slower)
 
* reported hours > allocated hours
 
  
Some task may have ''multiple assignments'' (more task participants). Task progress is calculated as average of all assignments. Assignments with more allocated hours have higher value. If task has no allocated hours, than only approximate value of progress is given, based on % progress and hours done.
+
'''blue:'''  
  
== Status of tasks, milestones ==
+
*Manual &lt;= Automatic (Task progress is faster or the same as planned)  
* [[file: 3.13.ikonaOpravljeno.JPG‎]] '''allocated''' - new task that user should accept first in order to be able to report hours.
+
*closed assignments: 100&nbsp;% progress
* [[file: Naloga_sprejeta.JPG‎]]'''accepted''' - user can report hours, enter comments
 
* [[file: 4.7.ikonaRdecKrizec.jpg‎]] '''rejected''' - task rejected by assignee. No hours can be reported. Project manager needs to confirm rejection.
 
* [[file: Ura.JPG‎]] '''done''' - assignee has done the task. Project managed needs to '''close''' or '''reject''' task (return to assignee). Assignee can '''cancel''' the status to '''accepted''' until it is closed.
 
* [[file: 4.2.9.ikonaKljukcaZelena.jpg‎]] '''closed''' - Project manager has reviewed done task and can '''close''' it for work reporting and editing. Project manager can close and evaluate the task, confirm eligible project hours.
 
** '''green''' - task was done in due date
 
** '''reed''' - task was late
 
  
====Important====
+
'''orange:'''  
* Project manager can any time close the task, regardless its status. By closing the task, no editing or reporting on hours spent is possible.
 
* '''Changes of task status''' are accessible at "show changes to task statuses".
 
  
===E-mail notifications on new and changed milestones, tasks ===
+
*Automatic &gt;= Manual (Task progress is slower)
'''E-mail settings''' are set in general settings of the application
+
*reported hours &lt;= allocated hours
  
*'''off:''' no e-mail are sent,
+
'''red:'''
*'''automatic:''' sends e-mail to all participants on the task and to project manager
+
 
 +
*Automatic &gt; Manual (Task progress is slower)
 +
*reported hours &gt; allocated hours
 +
 
 +
Some task may have ''multiple assignments'' (more task participants). Task progress is calculated as average of all assignments. Assignments with more allocated hours have higher value. If task has no allocated hours, than only approximate value of progress is given, based on&nbsp;% progress and hours done.
 +
 
 +
== Status of tasks, milestones  ==
 +
 
 +
*[[Image:3.13.ikonaOpravljeno.JPG]] '''allocated''' - new task that user should accept first in order to be able to report hours.
 +
*[[Image:Naloga sprejeta.JPG]]'''accepted''' - user can report hours, enter comments
 +
*[[Image:4.7.ikonaRdecKrizec.jpg]] '''rejected''' - task rejected by assignee. No hours can be reported. Project manager needs to confirm rejection.
 +
*[[Image:Ura.JPG]] '''done''' - assignee has done the task. Project managed needs to '''close''' or '''reject''' task (return to assignee). Assignee can '''cancel''' the status to '''accepted''' until it is closed.
 +
*[[Image:4.2.9.ikonaKljukcaZelena.jpg]] '''closed''' - Project manager has reviewed done task and can '''close''' it for work reporting and editing. Project manager can close and evaluate the task, confirm eligible project hours.
 +
**'''green''' - task was done in due date
 +
**'''reed''' - task was late
 +
 
 +
==== Important ====
 +
 
 +
*Project manager can any time close the task, regardless its status. By closing the task, no editing or reporting on hours spent is possible.
 +
*'''Changes of task status''' are accessible at "show changes to task statuses".
 +
 
 +
=== E-mail notifications on new and changed milestones, tasks  ===
 +
 
 +
[[File:Task_work_plan.JPG|400px|thumb]]
 +
'''E-mail settings''' are set in general settings of the application
 +
 
 +
*'''off:''' no e-mail are sent,  
 +
*'''automatic:''' sends e-mail to all participants on the task and to project manager  
 
*'''manual:''' new button is added '''SAVE AND NOTIFY''' - user can select who to sent notification. If you don't select and recipient, activity is saved and no e-mail is sent.
 
*'''manual:''' new button is added '''SAVE AND NOTIFY''' - user can select who to sent notification. If you don't select and recipient, activity is saved and no e-mail is sent.
  
[[file:4.3.1.DodajNalogo.jpg||400px]]
+
== Task relations  ==
  
== Task relations ==
 
 
Task can be interconnected. Child task is connected to parent task in tab of task pop-up: '''CORRELATIONS'''  
 
Task can be interconnected. Child task is connected to parent task in tab of task pop-up: '''CORRELATIONS'''  
  
Line 166: Line 188:
 
*if child task has hours entered, parent task cannot be re-opened.  
 
*if child task has hours entered, parent task cannot be re-opened.  
 
*If a task has child task, than end date of parent task cannot be changed.  
 
*If a task has child task, than end date of parent task cannot be changed.  
*Task can be edited if you remove correlations first, edit tasks and re-attach correlations.[[Image:4.3.1.KorelacijeNaloge.jpg|500px|4.3.1.KorelacijeNaloge.jpg]]
+
*Task can be edited if you remove correlations first, edit tasks and re-attach correlations.
 +
 
 +
== Milestones ==
  
==Milestones==
+
[[File:New_milestone.JPG|400px|thumb]]
Milestones are point in project course. The can be
+
Milestones are point in project course. It can be:
* stand alone milestone  
+
*stand alone milestone  
* end date of the phase (automatic)
+
*end date of the phase (automatic)  
* end date of task
+
*end date of task
Each milestone has one assignee.
 
  
===Add new milestone===
+
Each milestone has one assignee.
Click [[file:4.3.ikonaUstvariMejnik.jpg ]] to open a form.
+
 
# select activity,  
+
=== Add new milestone ===
# enter description
+
Click [[Image:4.3.ikonaUstvariMejnik.jpg]] to open a form.  
# select organization and assignee
+
#select activity,  
# set '''end date'''.  
+
#enter description  
 +
#select organization and assignee  
 +
#set '''end date'''.
  
 
If milestone repeats, select frequency of repetition and end date of the repetition.
 
If milestone repeats, select frequency of repetition and end date of the repetition.
 
[[file:4.3.1.DodajaMejnika.jpg|400px|]]
 
  
==Meetings==
+
== Meetings ==
Meetings are special type of project task with additional functionality that connect them to Calendar (Outlook)
+
[[File:New_meeting.JPG|thumb]]
 +
Meetings are special type of project task with additional functionality that connect them to Calendar (Outlook)  
  
===New meeting===
+
=== New meeting ===
Project meetings are organized in 4PM by clicing [[file:4.3.ikonaSkliciSestanek.jpg]] to open form:
+
Project meetings are organized in 4PM by clicing [[Image:4.3.ikonaSkliciSestanek.jpg]] to open form:  
 +
#select activity (meeting, board meeting),
 +
#enter meeting subject (task name),
 +
#enter task venue
 +
#date, start and end hours,
 +
#enter description and attach link to documents [[Image:IkonaPriponka.JPG]],
 +
#select meeting participants (send invitation to)
 +
and save.
  
# select activity (meeting, board meeting),  
+
4PM verifies the availability of participants in 4PM calendar (absence, another meeting). Once you save, 4PM sends e-mail invitation to Calendar (Outlook) and in My 4PM Calendar. Participants can enter hours for accepted meeting.  
# enter meeting subject  (task name),
 
# enter task venue
 
# date, start and end hours,
 
# enter description and attach link to documents [[file:IkonaPriponka.JPG]],
 
# select meeting participants (send invitation to)
 
and save.
 
  
4PM verifies the availability of invited participants in 4PM calendar (absence, another meeting). Once you save, 4PM sends e-mail invitation to Calendar (Outlook) and in My 4PM Calendar.
+
==== E-mail notifications for meetings  ====
Participants can enter hours for accepted meeting.
+
'''General application settings'''
 +
*ON – meeting invitation is sent to meeting invitees. Invitation can be accepted in Calendar and confirmation is sent to meeting organizer.  
 +
*OFF – no e-mail is sent, meeting appears only in 4PM.
  
====E-mail notifications for meetings ====
+
=== Meeting Confirmation ===
'''General application settings'''
+
General setting: DEFAULT INITIAL STATUS OF MEETINGS
*ON– meeting invitation is sent to meeting invitees. Invitation can be accepted in Calendar and confirmation is sent to meeting organizer.
 
*OFF – no e-mail is sent, meeting appears in 4PM.
 
  
===Meeting Confirmation===
+
*'''planned''': meeting must be confirmed  
General setting: DEFAULT INITIAL STATUS OF MEETINGS
 
*'''planned''': meeting must be confirmed
 
 
*'''confirmed'''
 
*'''confirmed'''
  
===Integration with mail client===
+
=== Integration with mail client ===
* Invited participants of the meeting receive '''meeting invitation'''. Invitation can be accepted or rejected in the e-mail client calendar. Reply is sent to organizer's mail.
+
 
 +
* Invited participants of the meeting receive '''meeting invitation'''.  
 +
* Invitation can be accepted or rejected in the e-mail client calendar. Reply is sent to organizer's mail.  
 
* Meeting organizer receives confirmed meeting to e-mail client calendar.
 
* Meeting organizer receives confirmed meeting to e-mail client calendar.
 
[[file:4.3.1.ObvestiloOutlooka.jpg|400px|]]
 
 
[[file:4.3.1.SklicSestanka.jpg|400px]]
 

Latest revision as of 08:46, 12 February 2016

Project plan

  • Project team members must perform certain activities to achieve project goals in set time frames. Project activities can be phases, work packages, tasks, milestones...
  • Preparing project schedule and Gantt-chart is simultaneous with task and activity allocation to team members. All corrections (dates, content) are available to team members in real time, with no delays.
  • Project team members use tasks for every-day collaboration and communication (entering comments, uploading and sharing project documents) and reporting (task progress reporting, hours done)
  • All information is archived, organized and available to use. All communication can be also sent by e-mails.

Project course is scheduled in 4PM and at the same time tasks and assignments are allocated to 4PM users in a transparent manner (in 4PM and by e-mail).

How to plan project schedule

Project task milestone tree.JPG

Project schedule (Gantt-chart) is made by the use of phases, tasks and milestones:

  • phase is created by clicking the icon 4.3.ikonaDodajFazo.jpg,
  • task click 4.3.ikonaDodajNalogo.jpg; to delegate task to one or more team members it should be assigned to project participants (add).
  • milestone click 4.3.ikonaUstvariMejnik.jpg,
  • meeting click 4.3.ikonaSkliciSestanek.jpg
  • Import and Export to Excel 4.3.ikonaIzvozInUvoz.jpg
  • click 4.3.ikonaDodaj(zelenKrogPlus).jpg to add child activity to phase.

Management of project phases

Phase can be:

  • a group of similar project activities (work package, WP)
  • group of activities in narrower time limit
  • smaller project (sub project)...

New phase

Phase edit new.JPG
  1. click icon 4.3.ikonaDodajFazo.jpg to open form.
  2. enter phase name and abbreviation
  3. select head of phase (from the list of participants),
  4. planned hours of work (optional)
  5. planned start and end date
  6. and short description.
Phase view.JPG
  • Each phase can have any number of sub-phases.4.3.ikonaDodajFazo.jpg
  • Head of the phase receives milestone for the phase end date.

Phase and cost planning and cost monitoring

  1. financial plan and cost can be monitored at the level of individual phases.
    • If financial plan is inserted first, later added phases inherit planned costs types in the value of 0. In this case, you can monitor the level of implementation of each phase, a comparison of the plan and implementation is at the level of the project.
  2. Financial plan and implementation can be monitored on the level of individual phase (work package).
    1. enter project activity plan by phases and activities (Gantt chart, project schedule)
    2. connect project activities with financial plan.

This is important for project management and reporting for co-financed projects.

Task management

Task is basic unit of the project with allocated resources. It represents an activity that is necessary to achieve project goal(s).

4PM uses task to:

  1. schedule project activities. Each task has set duration (start and end date), it has content (what to do) and one or more assigned participants. Task progress and status can be monitored
  2. collaboration and communication - by exchanging task comments and task documents. Integrated e-mailing systems enables effective communication in the group.
  3. daily reporting on work progress - each team member can access all relevant task information: task due date, allocated time and time spent, task progress of co-workers. Simple reporting forms enable time effective daily reporting and communication tool. Once a task is completed, a status is changed and notification sent to project manager.

New task

Click icon 4.3.ikonaDodajNalogo.jpg to open form. New tasks can be added in My 4PM/Insert/new task.

  1. select activity for task performance. Use list of project activities.
  2. enter task name (short description).
  3. set start and end date for the task.
    • if activity has set general duration (please check General/classification/list of activities) then application suggests end date (it can be changed)
    • if warning display for dates is on, then all dates must be within parent activity (phase, project)
    • if task does not have planned end date and allocated hours, it cannot used for resource load planning.
  4. optionally enter task description and
  5. attach links to documents
  6. select organization
  7. add assignees:
    • project participants (one or more) or
    • working groups (must be added to project).
  8. add number of available hours for a task for each individual
  9. optionally enter individual's task description (double click + confirm)
  10. confirm by 'ADD
  11. save and send e-mail notification to all task members.

Edit task

To change dates, add new task members, change description, add a comment, click task name to open task form in: any list of tasks, Gantt-chart, project course... Click 2.2.2.ikonaSvincnik.jpg to open task for editing.

Task details are accessible by clicking 2.2.2.ikonaLupa.jpg:

  • parent phase of the task
  • task reporter,
  • task duration,
  • list of task participants (assigned to) and state of task (task progress estimation)

Task and documents

Task can have links to documents:

  • that are up-loaded to 4PM (folder Tasks or any other project sub-folder that user can access
  • direct up-load to task in the field description or comments.

Comments - collaboration

Task comments.JPG

Team communication and collaboration is by task comments:

  • comments entered on a task (edit)
  • comments at project work reporting (daily description of work on task)
  • comments at task actions (accept, reject, done, finished, cancelled)
  • automatic comments on task actions

Comments can have links to documentsIkonaPriponka.JPG. Comments can be

  1. only saved to task or
  2. saved and sent by e-mail notification IkonaPismo.JPG to:
    • all team members
    • all task members
    • project manager.

Tasks and EU Projects

Tasks on EU projects need to have set cost field. To plan project activities you need to put financial plan to 4PM first with planned personnel costs and cost fiels.

Same task can have various cost fields set (each assignment needs to have set cost field).

  • double-click on the field cost field at assignment
  • select planned cost field
  • confirm 4.2.9.ikonaKljukcaZelena.jpg

Task progress

4PM supports two possibilities to monitor task progress and execution:

  • Automatic - assignment needs to have allocated (planned) hours (>0): task progress is automatically calculated at each work entry by formula: (hours done/allocated hours)*100.
  • Manual - each task participant enters personal estimation, which can be different from automatic.

Colours of task progress

blue:

  • Manual <= Automatic (Task progress is faster or the same as planned)
  • closed assignments: 100 % progress

orange:

  • Automatic >= Manual (Task progress is slower)
  • reported hours <= allocated hours

red:

  • Automatic > Manual (Task progress is slower)
  • reported hours > allocated hours

Some task may have multiple assignments (more task participants). Task progress is calculated as average of all assignments. Assignments with more allocated hours have higher value. If task has no allocated hours, than only approximate value of progress is given, based on % progress and hours done.

Status of tasks, milestones

  • 3.13.ikonaOpravljeno.JPG allocated - new task that user should accept first in order to be able to report hours.
  • Naloga sprejeta.JPGaccepted - user can report hours, enter comments
  • 4.7.ikonaRdecKrizec.jpg rejected - task rejected by assignee. No hours can be reported. Project manager needs to confirm rejection.
  • Ura.JPG done - assignee has done the task. Project managed needs to close or reject task (return to assignee). Assignee can cancel the status to accepted until it is closed.
  • 4.2.9.ikonaKljukcaZelena.jpg closed - Project manager has reviewed done task and can close it for work reporting and editing. Project manager can close and evaluate the task, confirm eligible project hours.
    • green - task was done in due date
    • reed - task was late

Important

  • Project manager can any time close the task, regardless its status. By closing the task, no editing or reporting on hours spent is possible.
  • Changes of task status are accessible at "show changes to task statuses".

E-mail notifications on new and changed milestones, tasks

Task work plan.JPG

E-mail settings are set in general settings of the application

  • off: no e-mail are sent,
  • automatic: sends e-mail to all participants on the task and to project manager
  • manual: new button is added SAVE AND NOTIFY - user can select who to sent notification. If you don't select and recipient, activity is saved and no e-mail is sent.

Task relations

Task can be interconnected. Child task is connected to parent task in tab of task pop-up: CORRELATIONS

  • End date of parent task must be one day before start date of child task.
  • If a task has allocated hours (or has status accepted) it is not possible to change task duration. Tip: First plan tasks with relations, later add task participants.
  • task relations are possible only within a phase
  • task assignee cannot accept child task until parent task is closed.
  • if child task has hours entered, parent task cannot be re-opened.
  • If a task has child task, than end date of parent task cannot be changed.
  • Task can be edited if you remove correlations first, edit tasks and re-attach correlations.

Milestones

New milestone.JPG

Milestones are point in project course. It can be:

  • stand alone milestone
  • end date of the phase (automatic)
  • end date of task

Each milestone has one assignee.

Add new milestone

Click 4.3.ikonaUstvariMejnik.jpg to open a form.

  1. select activity,
  2. enter description
  3. select organization and assignee
  4. set end date.

If milestone repeats, select frequency of repetition and end date of the repetition.

Meetings

New meeting.JPG

Meetings are special type of project task with additional functionality that connect them to Calendar (Outlook)

New meeting

Project meetings are organized in 4PM by clicing 4.3.ikonaSkliciSestanek.jpg to open form:

  1. select activity (meeting, board meeting),
  2. enter meeting subject (task name),
  3. enter task venue
  4. date, start and end hours,
  5. enter description and attach link to documents IkonaPriponka.JPG,
  6. select meeting participants (send invitation to)

and save.

4PM verifies the availability of participants in 4PM calendar (absence, another meeting). Once you save, 4PM sends e-mail invitation to Calendar (Outlook) and in My 4PM Calendar. Participants can enter hours for accepted meeting.

E-mail notifications for meetings

General application settings

  • ON – meeting invitation is sent to meeting invitees. Invitation can be accepted in Calendar and confirmation is sent to meeting organizer.
  • OFF – no e-mail is sent, meeting appears only in 4PM.

Meeting Confirmation

General setting: DEFAULT INITIAL STATUS OF MEETINGS

  • planned: meeting must be confirmed
  • confirmed

Integration with mail client

  • Invited participants of the meeting receive meeting invitation.
  • Invitation can be accepted or rejected in the e-mail client calendar. Reply is sent to organizer's mail.
  • Meeting organizer receives confirmed meeting to e-mail client calendar.